Articles

Crossrail to stagger opening

PE

On track: A detailed launch programme has already been drawn up for Crossrail
On track: A detailed launch programme has already been drawn up for Crossrail

Engineers and planners have devised a detailed launch programme that will minimise the risk of damage to the new railway's reputation


On track: A detailed launch programme has already been drawn up for Crossrail

Plans have already been put in place for Crossrail, as it approaches the halfway stage in terms of its construction, to avoid a repeat of the first-day fiasco that blighted the opening of Heathrow Terminal 5.

Although the first trains will not run on the new line until December 2018, Crossrail chief executive Andrew Wolstenholme said engineers and planning managers had already devised a detailed launch programme that would minimise the risk of damage to the new railway's reputation. This plan meant there would be no “big-bang” day one start of rail services that would put all the new civil, mechanical and electrical systems under pressure at the same time, he said.

Delivering the Lloyd’s Register foundation lecture in London at the end of last month, Wolstenholme, who led the delivery of the £4.3 billion Terminal 5 programme for BAA, said the mistakes on that project would not be made again. “Sensible lessons have been learnt from the past. You have to design in the 'soft-starts' [staggered starts] to get the track miles on the rolling stock, to get technical interfaces ironed out – and to do things in such a way so that the press don’t get the only story that they want, which is a failure on day one.”

Wolstenholme said the soft-starts meant the infrastructure would be eased in in a staged manner. “So when we talk about December 2018, that’s the stage three opening. Stage one is taking on the existing Liverpool Street to Shenfield services with existing rolling stock. Stage two is putting the new rolling stock on the existing line from Heathrow to Paddington above ground. And stage three is to put that rolling stock below ground. “A lot of attention is going into the reputational side of Crossrail.”

Wolstenholme said that similar careful thought had gone into the layout of the rolling stock. Crossrail will effectively act as a high-volume, high-throughput metro service in central London, but its link to Heathrow means it will also be expected to carry a lot of travellers with luggage. Those conflicting requirements have been a challenge in terms of how the interior of the new trains will look. “We have spent a long time researching what is ultimately going to be a hybrid train,” he said.

“If you currently get the 8.24 from Maidenhead, the orientation of your seat will be as a four with a table in between. If you get on the tube at Bond Street, then you will be sitting down longitudinally. So what we are trying to do is to mix and match the best orientation for all those journey types.

“There’s been a great debate around the space we have for luggage, and around whether or not we have toilets. I think people will begin to understand the geometry and layout of the rolling stock to be one that is highly suitable. It will be air-conditioned, it will be light and free: it will set a new benchmark.”

Wolstenholme said that Crossrail was in the middle of the procurement process for the £1 billion order for new rolling stock, with a decision due in the first quarter of 2014. There are three shortlisted bidders: Bombardier, based in Derby; Hitachi, which is building an assembly plant at Newton Aycliffe in the North East, where it will make the replacement rolling stock for Britain's ageing Intercity fleet; and CAF in Spain.

Wolstenholme said that the rolling stock was politically the most sensitive procurement contract of the entire Crossrail project.

Giant project spans capital

  • Crossrail is Europe’s largest infrastructure project, costing £14.8 billion.
  • The railway will deliver a high-frequency, high-capacity service of up to 1,500 passengers per train, linking Maidenhead and Heathrow in the west, to the City of London, Canary Wharf, and Shenfield and Abbey Wood in the east. 
  • The route will pass through 38 stations and run over 100km, with new, twin-bore 21km tunnels running through the central section.
  • Crossrail will increase London’s rail-based transport network capacity by 10%, supporting regeneration and cutting journey times across the city.
  • The project is delivered by Crossrail Limited, a subsidiary of Transport for London, and is jointly sponsored by the Department for Transport and Transport for London.
Share:

Professional Engineering magazine

Current Issue: Issue 1, 2024

01 Cover_Final online
  • How engineers are reinventing sport
  • Airbus engineer Sian Cleaver shoots for the Moon
  • Decarbonising aviation
  • Humanoid robots step out of the shadows

Read now

Professional Engineering app

  • Industry features and content
  • Engineering and Institution news
  • News and features exclusive to app users

Download our Professional Engineering app

Professional Engineering newsletter

A weekly round-up of the most popular and topical stories featured on our website, so you won't miss anything

Subscribe to Professional Engineering newsletter

Opt into your industry sector newsletter

Related articles